Delay Claims Now Go to Adjudication. So Does the Schedule.

By XNM Technologies · November 18, 2026 · 4 min read

For years, statutory adjudication in Ontario was mostly about getting paid. A contractor or subcontractor with an unpaid invoice could take the dispute to an adjudicator and get an interim decision quickly, long before a court or arbitrator would hear it. Since January 1, 2026, the process reaches much further into the substance of a project. Law firms that act for owners, contractors and consultants on capital projects now need their clients' project records to be ready for a fast, document-driven hearing on questions that used to wait until the end of the job.

Recent context

In a January 2026 bulletin, DLA Piper summarized amendments to Ontario's Construction Act that took effect on January 1, 2026, following the Building Ontario for You Act, 2024 and the Fighting Delays, Building Faster Act, 2025. According to that summary, adjudication now covers broader contract disputes, including the scope of work, changes to the contract price and extensions of time, with an exception for extension-of-time disputes under certain public-private partnership project agreements. Disputes about labour and material payment bonds can also be referred. The deadline to start an adjudication moves to 90 days after completion, abandonment or termination of the contract. Any party, not only contractors, can now require related adjudications to be consolidated if the adjudicators agree, and parties may jointly choose a certified private adjudicator instead of one from the registry. Determinations will also be made publicly available in anonymized form.

The same bulletin notes that an invoice is now deemed proper unless the owner gives notice of a deficiency within seven days, and that a notice of termination must be published within seven days of termination.

What changes for counsel

A payment dispute usually turns on a small set of documents: the contract, the invoice, the certificates and the payment history. A dispute over scope, price or time is different. It turns on what was in the drawings at tender, what the specification required, which instruction came first, when a site condition was found, what the schedule showed before and after, and who was told what and when. That evidence is spread across drawings, RFIs, site instructions, change orders, meeting minutes, daily reports, schedule updates and correspondence.

In litigation or arbitration, counsel has months to gather that material through production and discovery. Adjudication is built for speed. The party that starts the process and the party that responds both have to put a coherent story together from their own records in a short window. A client whose records are scattered across inboxes, personal drives and a site trailer is at a disadvantage before the adjudicator reads a word.

Public, anonymized determinations add another consideration. Over time they will show which kinds of evidence persuade adjudicators on scope and delay questions, and clients will be measured against that pattern.

A routine to put in place before the dispute

  1. Map the new deadlines. Add the seven-day invoice deficiency window, the seven-day termination notice and the 90-day adjudication window to the project calendar, so nobody learns about them from the other side.
  2. Keep one record of every change. Each change order, change directive and site instruction should be filed with its originating RFI or notice, the pricing, the approval and the related drawing revision, in one system that both the project team and counsel can open.
  3. Save the schedule as it was. Archive each baseline and each update with its date, rather than overwriting the file, so an extension-of-time question can be answered with the schedule that existed at the time.
  4. Write daily reports that would hold up in front of an adjudicator. Weather, crew counts, equipment, access problems and instructions received should be recorded on the day, by the people on site.
  5. Pull correspondence into the project file. Emails that give notice, accept a price or reject a claim belong with the contract record, not in one person's inbox.
  6. Run a mock referral once a year. Pick a live change or delay issue and ask how long it would take to assemble a complete submission. If the answer is more than a few days, fix the filing before it matters.

For the firm itself

Firms that advise on construction disputes can help clients by setting expectations at the start of a mandate: which records will be needed, in what form, and from whom. A standard intake list for scope, price and time disputes, shared with the client's project lead, shortens the first week of any referral. Firms that act for both owners and trades will also see the same weakness on both sides of the table: the evidence exists, but nobody can find it in one place.

The record is the argument

The amendments do not change what good project administration looks like. They change how quickly a weak record is exposed. Owners and contractors that keep drawings, contracts, changes and schedules in one auditable system give their counsel something to work with when a referral lands, and often avoid the referral altogether because the answer is already in the file.

This is general information, not legal advice. The Construction Act, its regulations and qualified counsel govern any particular dispute.